Business costing tool

Contract Manufacturing Job Cost Calculator

Turn materials, labour, overhead, setup, tooling and a scrap allowance into a full job cost, quote price and break-even quantity, instantly.

Cost-Plus Pricing Model Scrap Allowance Built In Break-Even Quantity Free To Use No Sign Up

Calculator Inputs

Cost Breakdown

ItemAmount% Of Cost
Materials--

Scenario Analysis

ScenarioQuote Price Per UnitChange
Current setup--

How Is The Job Cost Built Up?

The calculator adds four cost categories - materials, labour, overhead and fixed costs - across a scrap-adjusted production quantity, then applies your target margin to set the quote price. With a 3% scrap allowance, a 250-unit order needs 258 units started (250 ÷ 0.97, rounded up): that gives a material cost of £825.60 (258 × £3.20), 34.4 labour hours (258 × 8 minutes ÷ 60) costing £567.60 at £16.50/hour, and £368.94 of overhead (65% of labour cost). Add the £120 setup charge and £450 tooling cost and the total job cost is £2,332.14 - £9.33 per unit (see Worked Example 1 below).

Understanding The Burdened Labour Rate

Overhead - also called the "burden rate" - covers machine depreciation, factory rent, power, supervision and admin: everything that keeps a job running beyond the operator's wage. AccountingTools and Patriot Software both document overhead rates commonly ranging from roughly 25% to over 120% of direct labour cost, depending on how machine- and capital-intensive the process is. This tool applies your overhead rate as a straight percentage of labour cost, the standard simplified "burdened labour rate" method used in job-order costing.

Setting A Realistic Scrap Allowance

Shoplogix and MetricHQ both put a scrap rate under 5% as the widely used general manufacturing benchmark, with under 1% considered excellent in most sectors and high-precision work often expecting less. Scrap doesn't change what you bill the customer - it changes how many units you must start: a 250-unit order at 3% scrap needs 258 units produced, and if the true scrap rate turns out to be 6% instead, that same batch would need 266 units started to still deliver 250 good ones, eating directly into your margin if the price was fixed on the lower estimate.

Choosing A Target Margin

Equipment Calculators' CNC business benchmarks report typical UK CNC/job-shop net margins of 15%-35%, and Starter Story's contract manufacturing profitability report puts average gross margin for contract manufacturers around 30%. Target margin here is defined as gross margin - profit as a percentage of the final price, not a markup on cost - so a 25% margin on a £9.33 cost gives a £12.44 price, not the £11.66 a 25% cost-markup would give.

Why Batch Size Drives Unit Cost

Setup and tooling are fixed costs that don't scale with batch size. Spread across a 250-unit batch, £570 of combined setup and tooling cost is £2.28 per unit; spread across a 20-unit prototype run, a £150 setup cost alone is £7.50 per unit - over three times as much despite the total fixed cost being lower (see Worked Example 2 below). Doubling a batch size is usually the single biggest lever a job shop has for cutting unit price, which is why it's the first row in the Scenario Analysis table.

Method And Limits

This calculator uses a single-operation cost-plus model: one material rate, one labour rate and time, one overhead percentage, and two fixed costs (setup and tooling), scaled by a scrap-adjusted production quantity, using figures checked 2026-08-25.

  • Assumes one production operation. It does not model a multi-stage routing (e.g. turning, then heat treatment, then plating) where each stage has its own labour time, machine rate and scrap rate - for a multi-stage job, run the calculator once per stage and add the fixed costs together, or use a blended total labour time and overhead rate as an approximation.
  • Does not model carriage, packaging or duty. Delivery cost, packaging materials and any import duty on materials sourced from outside the UK are not included - add them to the material cost per unit or as an extra line on the final quote.
  • Scrap is a flat percentage of the whole batch, not stage-specific yield loss. A process with most of its scrap risk concentrated in one operation, rather than spread evenly across the batch, will not be represented precisely by a single scrap percentage.
  • Overhead is one percentage of labour cost, not full activity-based costing. Real overhead allocation can vary by machine type, floor space used, or energy consumption - this tool uses the simpler and more common "percentage of direct labour" method.
  • Does not add payment terms or currency risk. It does not model deposits, staged payments, early-payment discounts, or exchange-rate exposure on imported materials.

Figures checked .

Frequently Asked Questions

What counts as "overhead" in the overhead rate field?

Overhead (also called the "burden rate") covers everything that keeps the job running beyond the operator's wage: machine depreciation and running cost, factory rent and utilities, supervision, quality control and admin time. AccountingTools and Patriot Software both describe overhead rates from roughly 25% to well over 100% of direct labour cost depending on how capital-intensive the process is - a manual assembly job typically sits at the low end, and CNC machining or moulding with expensive machine time sits higher.

How is the scrap-adjusted production quantity worked out?

Divide the batch quantity you need to deliver by (1 minus the scrap percentage), then round up. A 250-unit order with a 3% scrap allowance needs 250 ÷ 0.97 = 257.7, rounded up to 258 units started, so that even after losing roughly 3% to scrap you still have 250 good units to ship.

What's a realistic scrap rate to enter?

Shoplogix and MetricHQ both put a scrap rate under 5% as the widely used general manufacturing benchmark, with under 1% considered excellent in most sectors and high-precision work often expecting less still. If you don't have your own historical scrap data for this process, 3-5% is a reasonable starting point; adjust it once you have a few completed batches to compare against.

Is my labour rate too low?

The calculator doesn't cap your labour rate, but it flags it against the statutory floor: the National Living Wage for workers aged 21 and over is £12.71/hour from 1 April 2026, rising to £10.85/hour for 18-20 year-olds and £8.00/hour for under-18s and apprentices, per gov.uk's National Minimum Wage rates page. A skilled machine operator or toolmaker's pay rate is normally well above this floor once skill and experience are reflected.

What margin should I actually target?

Equipment Calculators' CNC business benchmarks report typical UK CNC/job-shop net margins of 15%-35%, and Starter Story's contract manufacturing profitability report puts average gross margin for contract manufacturers around 30%. The Assessment module on this page reads your entered margin against that 15%-35% band: below 15% shows "Thin Margin," 15%-35% shows "Healthy Margin," and above 35% shows "Premium Margin."

Why does a small batch cost more per unit than a large one?

Setup and tooling are fixed costs - they don't change however many units you make. Spread across a 250-unit batch, £570 of combined setup and tooling cost is £2.28 per unit; spread across a 20-unit prototype run, a smaller £150 setup cost alone is £7.50 per unit - over three times as much per unit despite the total fixed cost being lower. This is the single biggest lever a job shop has on unit price: consolidating small repeat orders into one larger batch cuts the fixed-cost share sharply.

What does the break-even quantity tell me?

It's the number of units you'd need to sell at your quoted price just to cover the fixed setup and tooling cost, before any material, labour or overhead profit contributes. In Worked Example 1, 106 units covers the £570 fixed-cost pool at that price - since the batch is 250 units, the job clears break-even well before the full run, which is a useful sanity check before you commit to a tooling spend.

Is target margin the same as markup?

No. Target margin here is gross margin - profit as a percentage of the final selling price. A 25% margin on a £9.33 cost gives a £12.44 price (profit is 25% of £12.44). A 25% markup on the same £9.33 cost would instead give an £11.66 price (25% added on top of cost) - a materially different number. Check which convention your own costing spreadsheet uses before comparing figures.

Can I use this for injection moulding, sheet metal, or assembly work, not just CNC machining?

Yes. The cost structure - materials, labour, overhead, setup/tooling and scrap - applies to any batch manufacturing process. Tooling cost is typically far more significant for injection moulding (mould cost can run into thousands of pounds) than for simple assembly, but the calculator handles that the same way: enter your real tooling cost, whatever the process.

What if my job has no dedicated tooling at all?

Enter £0 in the Tooling cost field. Many jobs - manual assembly, standard off-the-shelf fixtures, simple sheet-cutting - need no dedicated tooling, and the calculator handles that correctly: the fixed-cost pool becomes the setup/changeover cost alone.

How accurate is the labour time estimate I should enter?

Use your own measured or estimated cycle time per unit, including load and unload time, not just cutting or moulding time. If you don't have a measured cycle time yet, time a small trial run of 5-10 units and use the average - a labour time estimate that's off by even 20% shifts a £16.50/hour, 8-minute-per-unit job's labour cost by over £1,300 across a 250-unit batch.

Does the scenario analysis account for compounding effects, like higher scrap slowing down labour too?

No - each scenario changes one variable at a time from your baseline inputs (batch size, material cost, labour rate, or scrap rate) and recalculates independently. Real-world cost increases often compound (a quality problem that raises scrap can also slow the line and raise labour time), so treat the scenario rows as individual sensitivity checks, not a combined worst case.

What happens if I set batch quantity to 0?

Every cost figure shows £0.00 and the Assessment status shows a waiting message asking for a batch quantity above 0, rather than showing a divide-by-zero error. Enter at least 1 unit to see a real result.

Should I trust this as my final customer quote?

Treat it as a costing worksheet, not a finished quote. It does not add VAT, carriage, packaging, payment terms, or currency risk on imported materials (see Method and limits above) - add those separately before the number goes on a customer-facing quote document.

Can I model a multi-stage job with more than one production process?

Not directly in one pass. Run the calculator once per stage using that stage's own labour time, rate and scrap rate, then add the resulting material, labour and overhead totals together and enter the combined setup/tooling cost as a single fixed-cost figure - see Method and limits for the same guidance.

Sources

Last updated: 2026-08-25. This page gives a costing estimate only and is not accounting, tax or financial advice.